A number of
significant changes have been introduced into this new issue of the standard which,
when taken together, have resulted in a significantly better document for the
arboriculturist, and so for the trees affected by the proposed development. By seeking to standardise the way arboricultural
matters and all the other issues in the planning process are dealt with the
standard may also help the project arboriculturist climb the ladder of esteem
with all the other professionals involved in a particular development proposal –
no longer will the arboriculturist be talking about a different timetable from
the designers and developers for example.
A significant
commercial consideration for all parties involved in the planning application
is that the standard suggests that the arboricultural method
statement with the application be submitted simply as heads of
terms as an acknowledgment
that the detail of the application may change as it is considered by the local
planning authority. Once planning
permission has been granted then greater input will be from the project
arboriculturist to produce a suitably detailed arboricultural method
statement, including an auditable
system for monitoring a schedule of specific site arboricultural events on
site. All parties need to understand
this shift in the balance of the arboriculturist’s work profile compared to the
requirements that have existed for the past 7 years under the 2005 release of
the standard.
The 2012 standard
states:
5.4 Arboricultural
impact assessment
5.4.1 The project arboriculturist
should use the information detailed in 5.2 [Constraints
posed by existing trees] and 5.3 [Proximity of structures to
trees] to prepare an arboricultural impact assessment that evaluates
the direct and indirect effects of the proposed design and where necessary
recommends mitigation.
5.4.2 The assessment should take
account of the effects of any tree loss required to implement the design, and
any potentially damaging activities proposed in the vicinity of retained trees.
Such activities might include the
removal of existing structures and hard surfacing, the installation of new hard
surfacing, the installation of services, and the location and dimensions of all
proposed excavations or changes in ground level, including any that might arise
from the implementation of the recommended mitigation measures. In addition to the impact of the permanent
works, account should be taken of the buildability of the scheme in terms of
access, adequate working space and provision for the storage of materials,
including topsoil.
and:
6 Technical design
COMMENTARY ON CLAUSE
6
Technical design [RIBA
stage E, see Table 1 below] includes
information sufficient to provide a high level of confidence in the outcome for
trees retained on development sites.
Where planning permission or other statutory controls apply, details
might need to be submitted in draft form or heads of terms to allow for changes to the design that
might occur after permission has been granted.
In these cases, it will be necessary for the project arboriculturist to
set out a series of parameters for construction activity (e.g. where service
routes and/or construction activity should not occur), based on the RPA and the
physiological needs of the tree, to which the finalized specifications and
statements will apply.
6.1.1 A precautionary approach
towards tree protection should be adopted and any operations, including access,
proposed within the RPA (or crown spread where this is greater) should be
described within an arboricultural method statement, in order to demonstrate
that the operations can be undertaken with minimal risk of adverse impact on
trees to be retained.
6.1.2 The arboricultural method
statement should be appropriate to the proposals and might typically address
some or all of the following, incorporating relevant information from other
specialists as required:
a) removal of existing
structures and hard surfacing;
b) installation of temporary
ground protection (see 6.2.3);
c) excavations and the
requirement for specialized trenchless techniques (see 7.7.2);
d) installation of new hard
surfacing – materials, design constraints and implications for levels;
e) specialist foundations –
installation techniques and effect on finished floor levels and overall height;
f) retaining structures to
facilitate changes in ground levels;
g) preparatory works for new
landscaping;
h) auditable/audited system of
arboricultural site monitoring, including a schedule of specific site events
requiring input or supervision.
6.1.3 The arboricultural method
statement should also include a list of contact details for the relevant
parties.
Stage of process
|
Minimum detail
|
Additional information
|
Pre-application (RIBA Work Plan stages A – D)
|
Tree survey
|
Tree retention/removal plan (draft)
|
Planning application (RIBA Work Plan stage D)
|
Tree survey (in the absence of pre-application
discussions)
Tree retention/removal plan (finalized)
Retained trees and RPAs shown on proposed layout
Strategic hard and soft landscape design, including
species and location of new tree planting
Arboricultural impact assessment
|
Existing and proposed finished levels
Tree protection plan
Arboricultural method statement – heads of
terms
Details for all special engineering within the RPA and
other relevant construction details
|
Reserved matters / planning condition
|
Alignment of utility apparatus (including drainage),
where outside the RPA or where installed using a trenchless method
Dimensioned tree protection plan
Arboricultural method statement – detailed
Schedule of works to retained trees, e.g. access
facilitation pruning
Detailed hard and soft landscape design
|
Arboricultural site monitoring schedule
Tree and landscape management plan
Post-construction remedial works
Landscape maintenance schedule
|
The standard suggests a number of minor changes to the parameters
required to be captured by the initial tree survey in clause 4.4.2,
for example:
·
the
exiting height above ground and direction of growth of the lowest branch is to
be recorded,
·
the way
that the estimated remaining life expectancy is expressed has been changed,
·
Category
U replaces R – whilst the trees may have no value there may well be no
overriding need to remove them.
In addition the standard changes the way the RPA is to be
calculated and plotted and no longer allows an RPA to be off-set but will
accept a modified RPA when it can be justified
(clause 4.6.3)
on defendable arboricultural grounds.
Table 1 below is an adaption of that included as Figure 1 on page 2 of the standard;
I have added the descriptions from the RIBA Plan of Work from http://www.pedr.co.uk/textpage.asp?menu=1a&sortorder=130&area=main viewed on 30 April 2012:
RIBA
work stages
|
Description of tasks under
RIBA plan of work
|
BS
5837 reference and clause number
|
Site
operations under
BS 5837
(clause number)
|
||
Preparation
|
A
|
Appraisal
|
Identification of client's needs and objectives, business
case and possible constraints on development.
Preparation of feasibility studies and assessment of options
to enable the client to decide whether to proceed.
|
Topographical
survey and soil assessment (4.2 and 4.3)
Tree survey (4.4)
Tree categorisation
(4.5)
|
Vegetation
clearance if required for survey.
|
B
|
Design brief
|
Development of initial statement of requirements into the
Design Brief by or on behalf of the client confirming key requirements and
constraints. Identification of procurement method, procedures, organisational
structure and range of consultants and others to be engaged for the project
|
Identify tree
constraints and root protection areas (4.5, 4.6 and Clause 5).
|
|
|
Design
|
C
|
Concept
|
Implementation of Design Brief and preparation of additional
data.
Preparation of Concept Design including outline proposals
for structural and building services systems, outline specifications and
preliminary cost plan.
Review of procurement route.
|
Identify and review
potential trees for retention and removal (Clause 6)
|
|
D
|
Design development
|
Development of concept design to include structural and
building services systems, updated outline specifications and cost plan.
Completion of Project Brief.
Application for detailed planning permission.
|
Produce new
planting and landscape proposals (5.6)
Produce tree
protection plan (5.5)
|
|
|
E
|
Technical design
|
Preparation of technical design(s) and specifications,
sufficient to co-ordinate components and elements of the project and information
for statutory standards and construction safety.
|
Resolve tree
protection proposals (6.2)
Agree new utility
apparatus locations, routes and arboricultural methodologies (6.1 and clause
7)
|
|
|
Pre-construction
|
F
|
Production information
|
Preparation of production information in sufficient detail
to enable a tender or tenders to be obtained.
Application for statutory approvals.
Preparation of further information for construction
required under the building contract.
|
Schedule trees for
removal and pre-construction tree works (including access facilitation (5.4
and 8.8)
|
|
G
|
Tender documentation
|
Preparation and/or collation of tender documentation in
sufficient detail to enable a tender or tenders to be obtained for the
project.
|
Identify tree
protection measures and include them in all relevant documents (6.2)
|
|
|
H
|
Tender action
|
Identification and evaluation of potential contractors
and/or specialists for the project.
Obtaining and appraising tenders; submission of
recommendations to the client.
|
|
|
|
Construction
|
J
|
Mobilisation
|
Letting the building contract, appointing the contractor.
Issuing of information to the contractor.
Arranging site hand over to the contractor.
|
Site monitoring and
intervention as required (6.3)
|
Physical barriers erected
(6.2)
Site clearance and
demolition (clause 7)
Access, storage and
working areas installed (clause 6)
|
K
|
Construction to practical completion
|
Administration of the building contract to Practical
Completion.
Provision to the contractor of further Information as and
when reasonably required.
Review of information provided by contractors and
specialists.
|
|
Construction
(clause 7)
New planting
(clause 8)
|
|
Use
|
L
|
Post practical completion
|
Administration of the building contract after Practical
Completion and making final inspections.
Assisting building user during initial occupation period.
Review of project performance in use.
|
Inspection of trees and surrounding environment (including
relationship to new structures) (8.8)
Recommendations for post-completion management (8.8)
|
Remedial tree works
if required
|
One thing that has
not changed with the introduction of the new standard is the opportunity for
carefully considered arboricultural interpretation at every stage of the
planning process when following the a particular development proposal.
No comments:
Post a Comment